Redstone Lighting
Rossland has entered a partnership with the Ministry of Transportation and Transit (MoTT) to deliver intersection lighting consisting of 7 cobra style lights to illuminate the Redstone Drive and Highway 3B intersection.

Municipal Services: Public Works
Josh Solman
Deputy Operations Manager
Email: deputy.operations@rossland.ca
Phone: 778-457-6624
The City is completing the detailed design and electrical servicing with MoTT completing the construction and ongoing ownership and operation.
Updates August 10-14, 2026
- Conduit install ongoing, approximate 300m installed to date
- MoTT lighting contractor scheduled to be on-site August 24th

Updates August 4-7, 2026
- Conduit install ongoing. Approximately 1/3 installed.

Updates July 20-24, 2026
- Conduit received at public works yard
- BC one call maps received
Updates this past week July 13-17, 2026
- Located underground power tie-in point on Redstone drive
- Conduit materials ordered
- Transformer pad received at works yard
- Scheduled start for utility install July 27th