Redstone Lighting

Rossland has entered a partnership with the Ministry of Transportation and Transit (MoTT) to deliver intersection lighting consisting of 7 cobra style lights to illuminate the Redstone Drive and Highway 3B intersection.

    Municipal Services: Public Works

Josh Solman

Deputy Operations Manager

Emaildeputy.operations@rossland.ca

Phone: 778-457-6624

 

The City is completing the detailed design and electrical servicing with MoTT completing the construction and ongoing ownership and operation.

Updates August 10-14, 2026

  • Conduit install ongoing, approximate 300m installed to date 
  • MoTT lighting contractor scheduled to be on-site August 24th

Updates August 4-7, 2026

  • Conduit install ongoing. Approximately 1/3 installed.

Updates July 20-24, 2026

  • Conduit received at public works yard 
  • BC one call maps received

Updates this past week July 13-17, 2026

  • Located underground power tie-in point on Redstone drive 
  • Conduit materials ordered 
  • Transformer pad received at works yard
  • Scheduled start for utility install July 27th